Notices must:
- Name the owners wishing to carry out the work and name your neighbours (adjoining owners)
- Clearly indicate the work to be done under the Act.
- State when the work is to be started.
- Be dated and signed.
- Where works under Section 6 are contemplated, be accommpanied by a drawing showing the position and depth of the proposed foundations.
- Where building immediately next to the boundary, describe the proposed wall, ie height, length and materials. This is probably best achieved by attaching a drawing to the Notice and making reference to it.
Notice periods are:-
- Section 1 - One month
- Section 3 - Two months
- Section 6 - One month
With your neighbour's agreement in writing you may start earlier.
So what happens next? Your neighbours, the adjoining owners,on receipt of your notice(s) have the following options:-
- Consent in writing within fourteen days (but may take longer).
- Consent with conditions (which may be refused) in writing within fourteen days but may take longer.
- Do nothing for fourteen days in which case a letter is sent to your neighbours giving them ten days in which to appoint a Surveyor.
- Dissent from the notice when they have to appoint a Surveyor within ten days.
Once Surveyors are appointed they will represent your interests but at the forefront of their minds must be the need to act independently ie the "wall" under Section 2 becomes their client rather than you.
When the building owner and the adjoining owner appoint the same Surveyor to act for them, the Act recognises this by conferring the title Agreed Surveyor. Where a real or deemed dispute arises between the parties, the Agreed Surveyor route is normally the cheapest and most efficient.
It is fallacious to believe that because the building owner normally pays the fees of the Surveyors, control over them is exercised. Party Wall Surveyors must act independently and if they fail to do so then an aggrieved owner can appeal any Award made by the Surveyors in the County Court.
Surveyor's fees must be reasonable and proportionate.
A point to remember- Building Owners do not have a right to place reinforced foundations (known as Special foundations) under any part of a wall belonging to an adjoining owner. This work requires specific written consent.
Another point often overlooked. There is nothing to stop neighbours agreeing to proposed works without notice being served BUT any such agreement must be written and clear in its meaning.